Action Step | Outcome(s) | Timeline |
1. Convert the 1960 Annex for school administrative use. | Business Office and Human Resources relocate to the second floor. | Start: Summer 2017 |
2. Move auction functions. | Auction occupies first floor annex. | Start: Spring 2019 |
3. Re-configure the Brothers' Community. | Bathroom renovation on Third Floor.
Creation of a small dining room on First Floor. | Start: Summer 2018 |
4. Establish Advancement, Alumni, Communications and President functions in Belcroft. | Alumni House no longer used for administrative functions. | Start: Fall 2018 |
5. Establish enrollment management functions in Belcroft. | Allinson House no longer used for administrative functions. | Start: Spring or Summer 2019 |
6. Re-configure the Alumni House propriety. | Creation of additional space for parking. | Start: Summer 2019 |
7. Re-purpose Allinson House as a campus welcome center. | Retain some functions the Brothers' House has offered on campus. | Start: First Floor, Summer 2019 Second Floor, Summer 2019-20 |
8. Renovate and re-purpose Dunleavy Center as for administrative housing or other dispositions. | Outside the scope of this plan but foreseen as completing the work on the four campus houses. | Start: Beyond 2021 |